Drammen Harbour

New container quay

Year

2008-2009

Size

2.114 m2 quay area + anchor- and friction slab

Extents

Assistance during erection

Særtrekk

Drammen Harbour has expanded their quay capacity with a new concrete container quay at the new container terminal at Holmen in Drammen. Design was executed by Svein Ove Nyvoll when employed in Dr. techn. Olav Olsen a.s and assistance during erection was carried out by Nyvoll Consult as a subcontractor of Dr. techn. Olav Olsen a.s.

Live load 50kN/m2
Quay length 140m
Piles ø610-16,0mm concrete filled hollow sections with length around 75m
Distances between piles 4,85x12,5mxx

Contract

Total contract

Nyvoll Consult as

Svein Ove Nyvoll

Emploier

AF Anlegg as

Contact

Lars Gunnar Andersen
Bjørn Lyngvær