Stadt Ship Tunnel

Stadt Ship Tunnel – Concept and Tender Phase

Year

2025–2026

Size

Ship tunnel with a length of 1,700 m, a navigable width of 26.5 m, and a navigable height of 33 m, including guiding structures.

Scope

Concept development of guiding and approach structures.

Specification

Repstad Anlegg AS is the contractor for Eiffage, one of the prequalified bidders for the Stadt Ship Tunnel project. Together with Dr. techn. Olav Olsen AS, Nyvoll Consult AS was engaged to develop the construction concept for the tunnel's approach and guiding structures, including fender systems and associated equipment.

 

The tunnel has a finished invert level of -13.25 m, a crown level of +36.75 m, and a width of 36 m. The work included developing constructible guiding structures within the tunnel, as well as guiding structures on both sides of the tunnel entrances. Particular focus was placed on the selection of fender systems in combination with the construction method and the concept for rock excavation.

Contract Type

Design and Build (Turnkey Contract)

Nyvoll Consult AS

Svein Ove Nyvoll

Client

Repstad Anlegg

Contact Person

Hans Christian