Year
2010–2011
Size
Foundation design and flood control for Vigeland Bridge in Lindesnes Municipality.
Scope
Verification of flood conditions during the construction period, as well as assistance with design and construction.
Specification
Vigeland Bridge is a new three-lane reinforced concrete bridge crossing the Audna River in the centre of Vigeland. The construction site is located in an area prone to flooding, and special attention was therefore given to flood management during the construction period.
Nyvoll Consult AS assisted AF Anlegg in adapting the foundation method and construction works to the river's water levels and flood conditions. In addition, Nyvoll Consult AS prepared procedures describing emergency preparedness and flood mitigation measures during the construction phase.
Contract Type
Main Contract
Nyvoll Consult AS
Svein Ove Nyvoll
Client
AF Anlegg
Contact Person
Gunnar Leirvik