Year
2014–2015
Size
Container / multipurpose quay.
Scope
152 m extension of the existing 180 m quay.
Specification
From 2014, Nyvoll Consult AS was involved in the extension of the existing container quay at Borg Havn. The project comprised the construction of a 152 m long quay aligned with the existing quay frontage. The new quay was built with a water depth exceeding 13 m at the quay face (mean sea level) and a width of 17 m. Two access lanes connecting the quay to the land were constructed, providing lateral support for the structure. Due to challenging ground conditions, concrete piles were installed beneath the landside area to ensure adequate protection against bearing capacity failure.
Nyvoll Consult AS was appointed as the client's structural engineering consultant during the preliminary design, tender, and construction phases.
Although the quay was primarily intended for container handling, the design also accommodates calls by larger cruise ships.
Construction commenced in 2014 and was completed in 2015.
Contract Type
Main Contract
Nyvoll Consult AS
Svein Ove Nyvoll
Client
Borg Harbour IKS
Contact Person
Tore Lundestad